BillingsJune 2026 · 10 min read

Over and Under Billing in Construction Accounting — Explained

Over-billings and under-billings are the most misunderstood concepts in construction accounting — and the most important. They determine whether a contractor's balance sheet is accurate, whether their financials are bankable, and whether they'll have a cash flow problem in three months.

The short version

Over-billing = contractor invoiced more than they've earned. It's a liability — money owed in future work. Under-billing = contractor earned more than they've invoiced. It's an asset — work performed but not yet billed. Both distort the P&L if not tracked properly.

Why this concept exists in construction

Most businesses recognize revenue when they invoice. Construction doesn't work that way. A contractor might bill 50% of a contract upfront to cover mobilization costs — but have only completed 20% of the work. If they recognize that full invoice as revenue, their P&L is misleading.

The solution is percentage-of-completion accounting: revenue is recognized as work is performed, not when it's invoiced. The difference between what's been billed and what's been earned creates either an over-billing or an under-billing.

Over-billing — the full explanation

An over-billing (also called "Billings in Excess of Costs and Estimated Earnings" or "Contract Liabilities" under ASC 606) occurs when a contractor has billed more than they've earned.

Over-billing = Billings to Date − Revenue Earned

Example: A $500,000 contract. The contractor has billed $250,000 but has only completed 30% of the work — meaning they've earned $150,000. The over-billing is $100,000.

That $100,000 is a liability. The contractor collected money for work they haven't done yet. If the job were cancelled tomorrow, they'd owe it back. It must appear on the balance sheet as "Billings in Excess of Costs" (or "Contract Liabilities").

Why large over-billings are a warning sign

A contractor with large over-billings often has a cash flow problem — they're billing ahead of their work to pay current expenses. Sureties call this "front-loading." When a project ends and the billings exceed what was earned, the contractor has to perform work without getting paid for it — and many can't.

Under-billing — the full explanation

An under-billing (also called "Costs in Excess of Billings" or "Contract Assets" under ASC 606) occurs when a contractor has earned more than they've billed.

Under-billing = Revenue Earned − Billings to Date

Example: Same $500,000 contract. This time the contractor has billed only $100,000 but is 40% complete — meaning they've earned $200,000. The under-billing is $100,000.

That $100,000 is an asset. The contractor has performed work they haven't invoiced for yet. It should appear on the balance sheet as "Costs in Excess of Billings" (or "Contract Assets"). While it looks good on paper, persistent under-billing creates cash flow pressure — the contractor is fronting labor and materials before collecting payment.

How to calculate over/under billings — the formula chain

1

% Complete (cost-to-cost)

Costs Incurred to Date ÷ Estimated Total Costs

2

Revenue Earned

Contract Amount × % Complete

3

Over-billing (if positive)

Billings to Date − Revenue Earned

4

Under-billing (if positive)

Revenue Earned − Billings to Date

A worked example — three jobs at once

Job
Contract
% Done
Earned
Billed
Apex Roofing
$180,000
65%
$117,000
$140,000
Pine Ridge
$95,000
40%
$38,000
$22,000
Harbor View
$240,000
20%
$48,000
$48,000
  • Apex Roofing: Billed $140K, earned $117K → Over-billed $23,000 (liability)
  • Pine Ridge: Earned $38K, billed $22K → Under-billed $16,000 (asset)
  • Harbor View: Earned = billed → Perfectly billed (rare)

How it appears on the balance sheet

Balance Sheet Line Item
What it represents
Costs in Excess of Billings (Current Asset)
Total under-billings across all active jobs — work performed but not yet billed
Billings in Excess of Costs (Current Liability)
Total over-billings across all active jobs — billed but not yet earned

These two balance sheet numbers must tie directly to the WIP schedule totals. If they don't, the financials aren't in balance. This is one of the first things a CPA or bonding underwriter will check.

How to track over/under billings in QuickBooks Online

QBO doesn't calculate over/under billings automatically. You need to:

  • Pull the Job Profitability Summary for actual income (billings) and actual costs
  • Pull Estimates by Customer for contract values and budgeted costs
  • Calculate % complete, revenue earned, and over/under billing outside QBO — usually in a spreadsheet or a WIP tool
  • Book a journal entry at month-end or year-end to record the over/under billing balances to the balance sheet accounts

Calculate over/under billings automatically

ReconcileBook connects to your client's QuickBooks Online and calculates over/under billings for every active job automatically — no spreadsheet, no manual formulas. The WIP schedule is ready in seconds and shows exactly which jobs are over-billed, which are under-billed, and by how much.

Questions about over/under billings? Email us or browse more guides.